This project focuses exclusively on the main home structure, involving a 7-square roofing return and critical exterior envelope upgrades. The technical roofing scope features a full-perimeter drip edge installation across all rakes and eaves to ensure superior moisture shedding. A modern ventilation profile will be established using ridge vents on all ridges, supported by a high-performance secondary water barrier of Ice and Water shields at all valleys, chimneys, and roof-to-wall transitions.
A significant portion of this assignment includes exterior carpentry and finishing:
- Window Remediation: Installation of five custom window wraps in White and the fitting of three window screens at designated locations.
- Hardware Preservation: The crew must exercise extreme caution to protect the existing gutter guards during the roofing process.
Site Management & Protection Protocols:
- Porch & Asset Shielding: Rigorous protection is required for the back porch, including all furniture, decor, and surrounding plant life. A/C units and decks must remain covered throughout the workday.
- Structural Safety: All roof access requires the use of ladder stabilizers to prevent damage to gutters and siding. To preserve the Fayetteville lawn, parking on the grass is strictly prohibited.
- Logistics & Professionalism: A Dump Trailer is mandatory for all debris. The crew must maintain a professional presence by wearing plain shirts and keeping a clean, organized workspace.
- Exhaustive Remediation: The project concludes with a “white-glove” cleanup, including blowing out all gutters and window seals. Any tar or scuff marks must be cleaned from the home’s exterior and walkways.
- Safety Sweep: Multiple magnetic roller passes are required across all driveways, sidewalks, and landscaped areas to ensure a 100% nail-free environment.
- Inventory: Please leave exactly three squares of shingles on the pallet for the homeowner.